Project Timeline

Throughout the project, Hallam Land and Dullatur Golf Club have been committed to engaging with the local community and stakeholders, using their feedback to shape proposals. Below illustrates key project milestones to date:

  • Feb 2021PoAN submitted to North Lanarkshire Council

  • May 2021First-stage Consultation

  • Sep 2021Planning Application Submitted to North Lanarkshire Council

  • Dec 2023First Community Liaison Group Meeting

  • Jan 2024Second Community Liaison Meeting

  • October 2024Expected Determination